The London Fire Brigade have been without any doubt the most useful of all bodies who have regulatory powers.
Once advised of the cladding at Garden Royal which was on 29th June 2021, they arranged to visit and make a detailed inspection.
Having completed the inspection, on 6th September 2021 they served a notice on the "responsible person" at Garden Royal.
The notice required that the necessary works should be completed by 7th March 2022. At September 2024 no works to ensure the safety of the Protected Fire Routes has been carried out.